According to Xuchang vehicle gas company annual planning, Xuchang gas filling station conducted the second phase expansion project on the basis of the origional facilities. On Apr.28, 2012, the company firstly made unified bid inviting in civil construction and equipment procurement ,etc projects, and commerenced construction on May.3. By Jun.13, the second phase of civil construction near the ened, CNG compressor, dryer, cooling tower, water treatment tank, etc equipments were already finished assembing and were lifted in place.
The project construction period is 4 months and expects to complete by the end of Auguest. After put into use, this project will benefits vehicle market expansion and meet the supply demands of gas sales.